• 2016

    ’16. 08 :  Completion Ceremony
    ’16. 06 : Acquired the plant operation license from IEAT allowing for the commencement of commercial production.
    ’16. 06 :  Hot Run
    ’16. 03 :  Cold Run

  • 2015

    ’15. 12 : Each facility was individually tested
    ’15. 11 : All required utilities for plant operation had been secured

  • 2014

    ’14. 10 : Ground-breaking Ceremony
    ’14. 09 : The ratification for EIA was received from ONEP
    ’14. 08 : Contracts for procurement and construction were concluded with POSCO family companies; POSCO E&C, POSCO ICT, and POSCO Engineering.
    ’14. 06 : Permission for investment was granted by the BOI
    ’14. 06 : Land usage permission was achieved from IEAT
    ’14. 03 : A purchase agreement for the plant site of 260,000 square meter was made with Amata City Industrial Estate

  • 2013

    ’13. 11 : POSCO Coated Steel (Thailand) Co., Ltd. was established.